One of the most challenging aspects of this project was the age and condition of the existing hot-rolled steel buildings on the premises. During the initial survey, we uncovered a number of old steel structures which had been dumped. The cladding in the existing buildings was from the 1970s and was not fit for purpose, and the roofing contained asbestos which needed to be professionally removed.
Firstly, we removed 10,000m2 of Asbestos roofing – this was disposed of safely and correctly using specific waste companies and specialist skips. All external buildings were also demolished and disposed of responsibly.